No development may start without an approved development permit unless Section 1.15 of the Land Use Bylaw exempts it; its exemption for new accessory buildings covers only those under 10 m² and no more than 4 m high. For a new commercial, industrial or institutional development, or the redevelopment of a parcel, the Town asks for a Pre-Consultation form first. A discretionary use, or a permitted use needing a variance, triggers notice to adjacent landowners. Decisions can be appealed to the Subdivision and Development Appeal Board within 21 days. Development must start within 12 months of the permit's issue and be completed within 24 months of starting.
Source: Town of Strathmore Land Use Bylaw No. 14-11 (Consolidated July 29, 2024, updated October 2, 2025)